Passage of Resolution ordering the work to proceed and adopting special assessments in the amount of $351,091 for the Hoyer Heights Residential Street Reconstruction Project No. 2317 (PV131).
-
Passage of Resolution requesting the Board of Estimate and Taxation authorize the City's issuance and sale of assessment bonds in the amount of $351,095 for the project.
-
Passage of Resolution ordering the abandonment and removal of areaways located in the public right-of-way in conflict with the project.
Consent
-
Capital project closeouts and appropriation and revenue adjustments within the City’s Capital Project, Enterprise, and Grant Funds (2019-01276)
Passage of Resolution amending the 2019 Capital Improvement Appropriation Resolution authorizing closure and appropriation adjustments for capital projects and programs, as indicated on Schedules A – D, and reallocations and redistributions of excess revenues and bond proceeds to projects requiring additional funding.
-
Request for Proposals for parking meter equipment and management system (2019-01277)
Authorizing issuance of a Request for Proposals (RFP) for parking meter equipment and a management system to support the equipment for the City of Minneapolis on-street parking system.
-
Request for Proposals for planning and engineering services for Hennepin Ave (Lake St W to Douglas Ave) Street Reconstruction Project (2019-01278)
Authorizing issuance of a Request for Proposals (RFP) for planning and engineering services for the Hennepin Ave (Lake St W to Douglas Ave) Street Reconstruction Project (PV158).
-
Mutual aid agreement with other public works agencies for training, preparation, and response to natural and man-made disasters (2019-01280)
Authorizing a mutual aid agreement with other metro-area public works agencies for training, preparation, and response to assist one another in the event of natural and man-made disasters, for a five-year period beginning Jan 1, 2020, and ending Dec 31, 2024.
-
Cost participation cooperative agreement with Hennepin County for North Loop Reconstruction Project (2019-01281)
-
Authorizing a cost participation cooperative agreement with Hennepin County, whereby the City will receive an amount not to exceed $125,000, for work completed as part of the North Loop Reconstruction Project No. 6766 (CPV135) along Washington Ave at the intersections of 7th, 8th, and 9th Aves N.
-
Passage of Resolution increasing the appropriation for the Public Works Department by $125,000.
-
-
Speed limit ordinance (2019-01092)
Setting a public hearing for Dec 3, 2019, to consider an ordinance amending Title 18, Chapter 474 of the Minneapolis Code of Ordinances relating to Traffic Code: Vehicle Operation, adding a new section on the process for establishing speed limits for city streets.
-
Southwest Windom Residential Street Reconstruction: Project designation, cost estimate, and setting public hearing (2019-01286)
-
Passage of Resolution designating the location and improvements proposed to be made in the Southwest Windom Residential Street Reconstruction Project No. 2307 (PV131).
-
Adopting report receiving cost estimate in the amount of $2,800,100, directing the preparation of proposed special assessments against the list of benefited properties, and setting a public hearing for Jan 21, 2020, to consider the project, assessments, and the abandonment and removal of areaways in conflict with the project.
-
-
Contract amendments with Custom Products and Services and Stonepros LLC for sidewalk and parking lot snow clearing, removal, and ice control services for Special Service Districts (2019-01287)
-
Authorizing an increase to Contract No. C-44482 with Custom Products and Services, in the amount of $540,720 for a total amount not to exceed $1,081,440, for sidewalk and parking lot snow clearing, removal, and ice control services for Special Service Districts for the 2019-2020 season.
-
Authorizing an increase to Contract No. COM0000009 with Stonepros LLC, dba Snowpros, in the amount of $620,400 for a total amount not to exceed $1,240,800, for sidewalk and parking lot snow clearing, removal, and ice control services for Special Service Districts for the 2019-2020 season.
-
-
Contract amendment with Meyer Contracting, Inc. for Hennepin Ave Water Main Replacement Project (2019-01288)
Authorizing an increase to Contract No. COM0000847 with Meyer Contracting, Inc., in the amount of $26,477.08 for a total amount not to exceed $588,383.13, for additional work for the Hennepin Ave Water Main Replacement Project due to unforeseen conditions and redesign of a hydrant location.
Receive & File
Receiving and filing a report of approved and implemented quarterly items for traffic zones, restrictions, and controls for the second quarter of 2019.
Discussion
-
Nicollet-Central Streetcar Project: Update (2019-01219)
Receiving and filing an update on the Nicollet-Central Streetcar Project.
-
2020 - 2022 Zero Waste Action Plan (2019-01283)
Receiving and filing the 2020 - 2022 Zero Waste Action Plan.
-
Americans with Disabilities Act Transition Plan for Public Works (2019-01284)
Receiving and filing an overview of the Draft Americans with Disabilities Act (ADA) Transition Plan for the Public Works Department.